Proceedings of the 2nd International Conference on Information, Control and Automation, ICICA 2022, December 2-4, 2022, Chongqing, China

Research Article

Study on the Investment Calculation Method of Water and Soil Conservation Measures Based on Monte Carlo Simulation Method

Download332 downloads
Cite
BibTeX Plain Text
  • @INPROCEEDINGS{10.4108/eai.2-12-2022.2327971,
        author={Xiaoyan  Yu and Min  Yu and Xiaoyong  Yang and Fuyan  Liu},
        title={Study on the Investment Calculation Method of Water and Soil Conservation Measures Based on Monte Carlo Simulation Method},
        proceedings={Proceedings of the 2nd International Conference on Information, Control and Automation, ICICA 2022, December 2-4, 2022, Chongqing, China},
        publisher={EAI},
        proceedings_a={ICICA},
        year={2023},
        month={3},
        keywords={monte carlo simulation method power transmission and transformation project water and soil conservation measures cost calculation method},
        doi={10.4108/eai.2-12-2022.2327971}
    }
    
  • Xiaoyan Yu
    Min Yu
    Xiaoyong Yang
    Fuyan Liu
    Year: 2023
    Study on the Investment Calculation Method of Water and Soil Conservation Measures Based on Monte Carlo Simulation Method
    ICICA
    EAI
    DOI: 10.4108/eai.2-12-2022.2327971
Xiaoyan Yu1, Min Yu1, Xiaoyong Yang1, Fuyan Liu1,*
  • 1: State Grid Zhejiang Power Co., Ltd.
*Contact email: fyanliu@163.com

Abstract

The construction and operation of soil and soil conservation measures are the prerequisite for the production and use of power transmission and transformation projects. However, the current cost of water and soil conservation measures in power transmission and transformation projects lacks the corresponding investment standards, which cannot effectively guide the power grid enterprises to scientifically formulate the investment scale of the cost of soil and water conservation measures, which is not conducive to improving the environmental protection benefits and economic benefits of the project construction by enterprises. In view of this, this paper systematically analyzes the framework of soil conservation measures for the completed water transmission and transformation project in the ZJ province and transformation project, proposes the investment and calculation method of the project, and finally, selects the temporary engineering measures as the research project to verify the effectiveness of the model method. This method and model can provide a basis for power grid enterprises to conduct soil and soil conservation management and investment estimation, reduce the economic loss and environmental damage caused by the unimplementation of soil and water conservation measures, and bring obvious economic and environmental benefits.

Keywords
monte carlo simulation method power transmission and transformation project water and soil conservation measures cost calculation method
Published
2023-03-27
Publisher
EAI
http://dx.doi.org/10.4108/eai.2-12-2022.2327971
Copyright © 2022–2025 EAI
EBSCOProQuestDBLPDOAJPortico
EAI Logo

About EAI

  • Who We Are
  • Leadership
  • Research Areas
  • Partners
  • Media Center

Community

  • Membership
  • Conference
  • Recognition
  • Sponsor Us

Publish with EAI

  • Publishing
  • Journals
  • Proceedings
  • Books
  • EUDL