Optimizing Of Time And Costs Of Building Construction Projects With The Alternative Of Additional Overtime Hours And Additional Workers

Download32 downloads
Cite
BibTeX Plain Text
  • @INPROCEEDINGS{10.4108/eai.9-9-2024.2359034,
        author={Eliatun  Eliatun and Dodi  Irfansyah and Darmansyah  Tjitradi},
        title={Optimizing Of Time And Costs Of Building Construction Projects With The Alternative Of Additional Overtime Hours And Additional Workers},
        proceedings={Proceedings of the 1st International Conference on Wetland for Sustainable Development Goals, ICWSDGs 2024, September 9th -- 10th, 2024, Banjarmasin, Indonesia},
        publisher={EAI},
        proceedings_a={ICWSDGS},
        year={2026},
        month={7},
        keywords={pdm crashing time and costs acceleration overtime analysis additional workers analysis},
        doi={10.4108/eai.9-9-2024.2359034}
    }
    
  • Eliatun Eliatun
    Dodi Irfansyah
    Darmansyah Tjitradi
    Year: 2026
    Optimizing Of Time And Costs Of Building Construction Projects With The Alternative Of Additional Overtime Hours And Additional Workers
    ICWSDGS
    EAI
    DOI: 10.4108/eai.9-9-2024.2359034
Eliatun Eliatun1,*, Dodi Irfansyah1, Darmansyah Tjitradi1
  • 1: Department of Engineering, Universitas Lambung Mangkurat, Banjarmasin, Indonesia
*Contact email: eliatun_tarip@ulm.ac.id

Abstract

This study was conducted on a new classroom construction project at SMKN 1 Kertak Hanyar, Tatah Amuntai District, at the request of the project owner to accelerate completion. The objective was to ensure the project is finished according to the initial schedule without disrupting the teaching and learning process. Two acceleration alternatives were evaluated in terms of cost and time efficiency: (1) extending working hours (overtime) and (2) increasing labor resources. The analysis began by identifying the critical path using the Precedence Diagram Method (PDM), followed by a crashing process to determine the cost slope of activities on the critical path. Under normal conditions, the project duration was 72 days with a total cost of IDR 298,406,296.70. Extending working hours by 2 hours on critical path activities reduced the duration to 62 days, with an increased cost of IDR 317,096,296.70. Meanwhile, adding four workers to critical path activities reduced the duration to 54 days at a cost of IDR 305,171,296.70. The results indicate that increasing labor resources provides a more optimal acceleration strategy compared to extending working hours, considering both cost and time efficiency.

Keywords
pdm, crashing, time and costs acceleration, overtime analysis, additional workers analysis
Published
2026-07-27
Publisher
EAI
http://dx.doi.org/10.4108/eai.9-9-2024.2359034
Copyright © 2024–2026 EAI
EBSCOProQuestDBLPDOAJPortico
EAI Logo

About EAI

  • Who We Are
  • Leadership
  • Research Areas
  • Partners
  • Media Center
  • Cookie Preferences

Community

  • Membership
  • Conference
  • Recognition
  • Sponsor Us

Publish with EAI

  • Publishing
  • Journals
  • Proceedings
  • Books
  • EUDL