Time And Cost Optimization with The Integration of Building Information Modeling (BIM) 4D and Time Cost Trade-Off Methods (Case Study: Pemali Bridge Project)

Download229 downloads
  • @INPROCEEDINGS{10.4108/eai.23-11-2022.2342989,
        author={Danniel Robby Dennis Andrean Napitupulu and M. Fanshurullah Asa and Ranny  Adriana},
        title={Time And Cost Optimization with The Integration of Building Information Modeling (BIM) 4D  and Time Cost Trade-Off Methods (Case Study: Pemali Bridge Project)},
        proceedings={Proceedings of the International Conference on Sustainable Engineering, Infrastructure and Development, ICO-SEID 2022, 23-24 November 2022, Jakarta, Indonesia},
        publisher={EAI},
        proceedings_a={ICO-SEID},
        year={2023},
        month={12},
        keywords={bridge construction management optimization 4d bim time cost trade-off},
        doi={10.4108/eai.23-11-2022.2342989}
    }
    
  • Danniel Robby Dennis Andrean Napitupulu
    M. Fanshurullah Asa
    Ranny Adriana
    Year: 2023
    Time And Cost Optimization with The Integration of Building Information Modeling (BIM) 4D and Time Cost Trade-Off Methods (Case Study: Pemali Bridge Project)
    ICO-SEID
    EAI
    DOI: 10.4108/eai.23-11-2022.2342989
Danniel Robby Dennis Andrean Napitupulu1, M. Fanshurullah Asa1,*, Ranny Adriana1
  • 1: Departement of Civil Engineering, Faculty of Infrastructure Planning, Pertamina University, South Jakarta, Indonesia
*Contact email: m.fanshurullahasa@universitaspertamina.ac.id

Abstract

Time and cost are highly calculated factors as indicators of project success. The presence of the COVID-19 pandemic has had an impact on the process of completing the Pemali Bridge project, a part of the Brebes-Tegal North Ring Road Project, which has stalled for many years. On this study, time and cost optimization using the 4D BIM method and Time Cost Trade-Off. Bridge Modeling in 3D and 4D levels are conducted using BIM 3D and 4D software. Meanwhile, time and cost analysis using spreadsheet and project management software. These results showed that the efficiency of reinforcement and concrete materials had an average value of 5% and an acceleration of the optimum duration of 13 days with the addition of 2 hours of work. These are evidence that the integration of BIM and Time Cost Trade-Off methods are effective for the cost and efficiency of construction project work.