Identification of Key Factors in Construction Progress of Undercrossing Existing Railway Lines under Frame Bridges

Download207 downloads
Cite
BibTeX Plain Text
  • @INPROCEEDINGS{10.4108/eai.15-3-2024.2346553,
        author={Xiaofang  Zheng and Xiaozhong  Li},
        title={Identification of Key Factors in Construction Progress of Undercrossing Existing Railway Lines under Frame Bridges},
        proceedings={Proceedings of the 4th International Conference on Public Management and Intelligent Society, PMIS 2024, 15--17 March 2024, Changsha, China},
        publisher={EAI},
        proceedings_a={PMIS},
        year={2024},
        month={6},
        keywords={crossing the existing railway line under the framework bridge; construction progress; complex network model},
        doi={10.4108/eai.15-3-2024.2346553}
    }
    
  • Xiaofang Zheng
    Xiaozhong Li
    Year: 2024
    Identification of Key Factors in Construction Progress of Undercrossing Existing Railway Lines under Frame Bridges
    PMIS
    EAI
    DOI: 10.4108/eai.15-3-2024.2346553
Xiaofang Zheng1,*, Xiaozhong Li1
  • 1: Lanzhou Jiaotong University
*Contact email: 17863608393@163.com

Abstract

Firstly, based on the model of "Driving force-State-Response" (DSR), take the construction parameters as the driving force indicators, the construction progress as the state indicators, and the construction progress enhancement measures as the response indicators, and construct the construction progress system of the frame bridge crossing the existing railroad line; secondly, take the driving force indicators and response indicators as the object of analysis, and combine the C-OWA operator method and CRITIC method to construct the complex network model. Secondly, taking the driving force indicators and response indicators as the analysis object, combining the C-OWA operator method and CRITIC method to construct a complex network model, determining the importance of the driving force and response elements' own nodes, the intensity of the influence between the nodes and the comprehensive importance of the nodes in turn, and determining the key influencing factors of the construction progress of the frame bridge crossing the existing railroad line project; finally, taking the empirical analysis of the construction progress of a frame bridge crossing the established railroad line project, and analyzing the results of the study.

Keywords
crossing the existing railway line under the framework bridge; construction progress; complex network model
Published
2024-06-07
Publisher
EAI
http://dx.doi.org/10.4108/eai.15-3-2024.2346553
Copyright © 2024–2025 EAI
EBSCOProQuestDBLPDOAJPortico
EAI Logo

About EAI

  • Who We Are
  • Leadership
  • Research Areas
  • Partners
  • Media Center

Community

  • Membership
  • Conference
  • Recognition
  • Sponsor Us

Publish with EAI

  • Publishing
  • Journals
  • Proceedings
  • Books
  • EUDL